Search  |  Sitemap  |  Contact us  |  Log in  |  Sign up
products & services industry solutions media centre about us
 
FlexLink Worldwide

Increasing production at GKN
Installing new machines and a conveyor line increased the daily production from 3300 to 4200 pieces.

GKN is one of the world’s leading automotive transmission suppliers. Their project engineers and maintenance staff in Offenbach and Mosel plants have preferred FlexLink when it comes to flexible and space saving material handling solutions for many years.
 
Short delivery time, easy build and technical support
The comprehensive range of FlexLink products, the short time of delivery and the fact that it is easy for GKN’s own staff to rebuild or build new lines with our components, are other reasons for choosing FlexLink. Our technical experts are also of course always at the customer’s disposal when needed.

GKN demands machine builders to use FlexLink conveyor systems
Through the good experience of the FlexLink installations, GKN demands more often that their machine builders shall supply their machine tools equipment with FlexLink conveyors system. One example is the transports to, from and between the machines and also in the buffering. It is of special importance for GKN that the conveyor technique and the linking between machines and lines have a uniform system, for working environment safety reasons and from a visual point of view. 

Increased production achieved within a few weeks
In 1998, the AM-1 line for working of raw material at the Waldhof plant was completely changed within a few weeks and a new one was installed. Through the installation of new machines for the inner and outer working of cardan shafts, in combination with a new transport between machines and the modified conveyor line, an increase of production from 3300 to 4200 pieces per day (25%), was achieved.

 

Legal © Copyright 2008 FlexLink. All rights reserved.