A FlexLink line was installed in the Göteborg plant, Sweden, for
the machining of the synchronized sleeves to all gearboxes. “When
starting a new project, we don’t always know exactly where the
lines will be installed in the plant”, says Stefan Bofeldt, project
engineer and responsible for the layout of the new SAAB line. “The ability to make a high quality product at medium production
levels at a competitive cost level together with the possibility to
make short set-up time. To replace an old line took between 2-3
weeks before, which is now cut down to 1-1 1/2 weeks, due to the
ever-increasing production volumes. This is why we need a flexible
ability to install a new system in a couple of days instead of
weeks.”
FlexLink, a flexible supplier
“FlexLink is a supplier that is flexible enough to continuously
adapt the layout to our changing needs during a project. FlexLink
starts the installation at the same time as the machines are being
put down in the factory. The fact that everything is built on the
spot and tailor made means that the real positioning of the
different machining cells is a great advantage.” One operator running the whole line
The production will be running in two or three shifts,
comprising eight different machining operations: turning,
broaching, cold forming, turning, pointing, hobbing, deburring and
shaving. The line is equipped with a FlexLink steel chain size XM
with cleated elevators provided with drip trays to eliminate any
leakage together with integrated cable
conduits. “One advantage with the FlexLink line is that no transfer is
needed to separate vertical elevators and have the ability to
buffer up to 20 minutes of production between the major machining
cells”. “This type of layout will be used for all high volume
cells in the future, since our production targets are continuously
increasing. Key success factors
“The ability to make a high quality product at medium production
levels, at a competitive cost level and make changes with a short
set-up time. To replace an old line took between 2-3 weeks before,
which is now cut down to 1-1 1/2 weeks, due to the ever-increasing
production volumes. This is why we need a new system that we can
install in a couple of days instead of weeks.” |